Starting more than 28 days after commencement notice

Home Forums Ireland Starting more than 28 days after commencement notice

  • This topic has 2 replies, 3 voices, and was last updated 16 years ago by Anonymous.
Viewing 2 reply threads
  • Author
    Posts
    • #709927
      Dee2007
      Participant

      Hi, what are the implications of starting self build more than 28 days after you send in the commencement notice. It looks like I’ll be delayed about 2 months. What does the LA do?

      Thank you,

      D

    • #799897
      Anonymous
      Inactive

      The are no significant implications. But i would send an explanitory letter to the LA anyway with a revised commencement date.

    • #799898
      Anonymous
      Inactive

      @henno wrote:

      The are no significant implications. But i would send an explanitory letter to the LA anyway with a revised commencement date.

      Or just dig a bit of a hole where you are intending on doing the work and you have commenced. The only other involvement the planners might have is a request to see the foundations being poured but this happens very seldom and they will ring you for an approximate date anyway so you can just tell them there is substantial ground works to be carried out first.