The Strategy document contains the following information on the comencement/completion dates for the remainder of the streetscape works in the city centre.
Upper Thomas St, Catherine St, Foxes Bow, Limerick Lane, and Erson’s Lane. Start Jan 2008 Finish Jan 2009
Sarsfield St, William St, and Upper William St. Start June 2008 Finish June 2009
O’Connell St, Patrick St to Crescent. Start March 2009 Finish December 2010
John’s Square. Start October 2009 Finish October 2010
Roche’s St, Shannon St, from Henry St to O’Connell St. Start Jan 2010 Finish Jan 2011
Catherine St between Glentworth St and Roche’s St. Start April 2009 Finish January 2010
Night Club Quarter. Start October 2008 Finish April 2010
To complete the Riverside Walks as follows:
Clancy Strand, Curragour Bund. Start October 2007 Finish October 2008
O’Callaghan Strand. Start January 2008 Finish January 2009
Shannon Bridge to Sarsfield Bridge incld. Lower Shannon and Cecil St. Start Oct 2008 Finish Oct 2009
Clancy Strand Boardwalk. Start May 2008 Finish November 2008
Bridge Lighting. Start October 2008 Finish April 2009
Merchants Quay / Potato market. Start October 2009 Finish October 2010