What to do if the PA is late?
- This topic has 5 replies, 5 voices, and was last updated 17 years, 11 months ago by
Anonymous.
- AuthorPosts
- December 19, 2007 at 8:30 am #709737
Francesburton
ParticipantThe planning authority took almost 9 weeks before rejecting my application. The application was valid and no FI was sought. By law I think they had to give a decision within 8 weeks or the decision would be granted by default.
Is this still the case?
And if so, what do I do next? - December 19, 2007 at 10:06 am #796397
Anonymous
InactiveDid the Authority acknowledge receipt of the application prior to the 9 weeks ?. Please refer to Part III S.34 of the planning and development act 2000.
- December 19, 2007 at 10:12 am #796398
Anonymous
Inactiveperhaps give us the ‘valid application receipt date’ and the ‘decision date’……??
- December 19, 2007 at 2:46 pm #796399
Anonymous
InactiveThe application was accepted on 19/10/07 and the due date was 13/12/07. The decision was given on 18/12/07.
- December 19, 2007 at 4:00 pm #796400
Anonymous
Inactivewhen you say ‘given’ do you mean when you actually received the decision??
The LA have 3 working days from the date of decision to get the decision to the applicant, .. the 13th of December was a Thursday… 3 working days from then is Tuesday 18th December.. the date you recieved the decision…
So i read the situation as being legally OK from the LAs point of view.
- December 20, 2007 at 5:40 pm #796401
Anonymous
InactiveI tought the burden to “get” the decision “to” the applicant was scrapped – is this not so ? The decision exists outright does it not . Makes sense in this information age
- AuthorPosts
- You must be logged in to reply to this topic.