@layo wrote:

The line capacity at the moment is already at its absolute limit. Bringing a hugely busy spur line to an already constricted bottle neck (Connolly st. to south of loop line bridge) would just be impossible unless massive engineering works were undertaken to 4 track the entire line to say Bray.

It is also annoying that people are still seeing the Metro North as a line that ONLY serves Dublin airport. Its main passenger base will be commuters from north county Dublin who have for years been poorly serviced by public transport. This is the main reason that it is being built and it is a very negative connotation to view the Metro as an airport only connection line.

I do believe though that the Interconnector heavy rail DART line is a much more important infastructure, and is obviously being viewed as such by the EU as it is receiving funding under the TEN-T 2009 programme. http://www.transport21.ie/Projects/Heavy_Rail/DART_Underground.html

http://www.railusers.ie

As someone who was involved with Rail Users Ireland in their embryonic days I am up to speed with the costs and user levels of the various options.

The reason the Northern Line is at capacity is that there are a number of train types using the line at different speeds i.e. trains going non-stop to Drogheda, non-stop to Howth Junction or stopping at every station en route. Trains to Dublin airport could easily be accomodated if they ran non-stop to Howth Junction and then stopped only at Dublin Airport if they ran 2 minutes behind Trains running to either Drogheda or Howth Junction that didn’t stop at each station.

Getting a connection to the City Centre from the airport is the objective not operating a train that becomes a Dart as soon as it hits trhe northern line; do people in Raheny have a god given right to a no-change route to the airport or do people in DCU have a similar right?

I also question your usage patterns on the North Commuter rail belt which excluding Swords is a series of quaint but small villages in the greater scheme of things. Look internationally there are very few international cities with a similar population to Dublin and none that I know of with similar development patterns that have ever spent this scale of expenditure on an underground rail link that wasn’t a 5kms or less project interconnecting two irrationally split rail systems.

I would love to see each kilometer of the metro be analysed on cost benefit grounds and each station’s projected passenger numbers as a proportion of the local population to see what contribution each station makes to operational revenues.