N28 to Ringaskidy has been stalled at route selection stage for 12 months at least
http://www.nra.ie/RoadSchemeActivity/CorkCountyCouncil/N28RingaskiddytoCork/SchemeName,11559,en.html
NRA Order of Progress for road projects is: Constraints Study, Route Selection, Preliminary Design, Tender, Construction, Complete.
Couldn’t even hazard a guess as to when it will be built