    Does anyone know why it is taking sooooo long for Eyre Square’s landscaping? I heard it won’t be finished until November, if we’re lucky. Why did they have to use chinese granite? What’s wrong with Irish granite? :confused: Me mother thinks it’s a disgrace.

    Is it just me or are all the best buildings, architectually, in Galway are in Shop St. and the street that you are in :confused: if you keep walking? The name, Spanish Arch, is misleading, don’t you think? You’d expect a graceful Baroque arch but all you get is a plain one. 🙁

    #752129
    Anonymous
    Inactive

    @Boyler wrote:

    Does anyone know why it is taking sooooo long for Eyre Square’s landscaping? I heard it won’t be finished until November, if we’re lucky. (

    Prophetic words

    http://www.rte.ie/news/2005/0405/galway.html

    Eyre Square workers in wage row

    05 April 2005 17:07
    Talks are taking place in Galway to try to resolve a dispute which has brought work on the city’s Eyre Square redevelopment programme to a virtual standstill.

    Thirty workers employed by the main contracting firm, Samuel Kingston Construction, have walked off the site in a row over wages.

    The workers, 19 Irish and 11 Polish, claim some of the workforce were not paid last week and others were only paid part of the wages due to them. They say they will not return to work until the issue is resolved.

    A small number of sub-contractors are still at work today.

    Samuel Kingston Construction has so far made no statement on the dispute, but the men were called to talks with local management this morning.

    Galway Corporations says the management of the workforce is a matter for the company.

    #752130
    Boyler
    Participant

    Just thought I would write something. I don’t want thread to go away.

    #752131
    nono
    Participant

    chinese granite is ‘cheaper’ despite the exorbitant cost of brining it a few thousand kilometres from china as opposed to a few hundred from wicklow (or somewhere similar) as it is extremely heavily subsidised by the powers that be in china, ie probably exported at a net loss, but china gains valuable foreign currency. 😀

    #752132
    Anonymous
    Inactive

    @nono wrote:

    chinese granite is ‘cheaper’ despite the exorbitant cost of brining it a few thousand kilometres from china as opposed to a few hundred from wicklow (or somewhere similar) as it is extremely heavily subsidised by the powers that be in china, ie probably exported at a net loss, but china gains valuable foreign currency. 😀

    The subsidy you talk of is a rural population of in excess of 600m people who work for about $1.50 a day, Chinese granite is cheaper because it is possible to finish the product by hand at a cost that wouldn’t get the average quarry worker out of bed in the morning. The Chinese Currency is contrary to what you might think being kept artificially low at the moment i.e. they have too much foreign currency at present.

    The problem I have with Chinese granite is the colour it is simply too pale for what we are used to in Ireland.

    #752133
    PaulC
    Participant

    Does anyone have any photographs of completed sections of the Square, or even drawings of what the proposed redevelopment will look like?

    #752134
    nono
    Participant

    thanks for the info thomond park

    #752135
    Anonymous
    Inactive

    Some sketches / plans available from the landscape architects site, mitchell & associates:

    http://www.mitchell.ie/site/eyre_square.asp

    A fair way to go from what i could see yesterday, right in the middle of things at the moment, have a few pics and will post them later.

    #752136
    PaulC
    Participant

    Thanks for that Peter – the plans certainly looks nice.

    #752137
    Anonymous
    Inactive

    a few shots taken on monday …

    #752138
    Boyler
    Participant

    You can make out what it will look like in November. It will be great to use the park again.

    #752139
    Anonymous
    Inactive

    http://www.rte.ie/news/2005/0627/galway.html

    More difficulty for Eyre Square redevelopment

    27 June 2005 12:11
    The controversial €9m redevelopment of Eyre Square in Galway city has run into further difficulty.

    Work on the site has come to a standstill following the withdrawal of staff employed by the main construction company, Samuel Kingston Construction.

    Galway City Council says it is shocked that Samuel Kingston Construction has abandoned the project and it will now have to find another company to complete the work

    Work on the redevelopment of the square began in May of last year and was due for completion this October.

    There has been constant criticism of the project because of the slow progress of the work and the major disruption it has caused to local businesses. Ends

    #752140
    Anonymous
    Inactive

    http://home.eircom.net/content/irelandcom/breaking/5810432?view=Eircomnet

    Workers walk off Eyre Square development
    From:ireland.com
    Monday, 27th June, 2005

    Construction workers on the controversial €9 million Eyre Square redevelopment in Galway city today walked off site.

    Work on the city centre refurbishment ground to a halt after teams of builders failed to man the job.

    A spokesman for Galway City Council said officials were seeking legal advice after employees from Samuel Kingston Construction walked off.

    He said the workers had abandoned the job without notice. “Galway City Council wishes to express our deep disappointment and annoyance at the decision of Kingston Construction to walk off-site at Eyre Square despite repeated and ongoing attempts with the contractor to secure the completion of the contract by the November deadline,” he said.

    The spokesman said no warning had been given of the stoppage. And he said all work carried out on-site, under terms of the contract, had been paid for in full by Galway City Council.

    Work on the redevelopment of the square began in May of last year and was due to be completed by November. But the redevelopment has been dogged by criticism from the outset due the slow pace of work and the massive disruption to businesses in the city centre.

    The Health and Safety Authority carried out a number of inspections at Eyre Square over the last year. No safety issues were identified by the HSA that would warrant the site being closed.

    Earlier this year workers, some of whom are Polish, walked off site in a row over wages. Ends

    #752141
    FIN
    Participant

    and the fun just keeps going.. now there is no contractor….seemingly kingston went bankrupt.

    #752142
    Boyler
    Participant

    I bet we’ll be waiting another month before work will start again. Is it true that Kingston was paid a million euros just last Friday?

    #752143
    Anonymous
    Inactive

    surely the landscape architects – mitchell & associates – would have been heavily involved supervising the implementation & should have had some indication re the situation with the contractor ?

    #752144
    Anonymous
    Inactive

    Samuel Kingston Construction Ltd. Address:, Unit 3N Kinsale Commercial Park
    Knocknahobilly Kinsale Co. Cork. Phone:, 00353 21 4779151

    I’ve heard that contract enforcement should be sought, one feels a lot of sympathy for local authorities at times

    #752145
    Anonymous
    Inactive

    http://www.rte.ie/news/2005/0701/galway.html

    New Eyre Square task force set up

    01 July 2005 20:00
    A new Mayoral task force has been set up in Galway to try to resolve the continuing problems surrounding the re-development of Eyre Square.

    The move comes after the decision of the main contractor to abandon the project earlier this week.

    Seven of the city’s leading businessmen are to join the team which will try to minimise the damage being caused to business and tourism as a result of this latest setback to the highly controversial €6.5 million scheme.

    Mayor Brian Walsh said the members of the task force would use their business expertise and no-nonsense approach to try to find solutions to the complex problems which had arisen in relation to the refurbishment of the square.

    Galway City Council has already brought in a firm of outside contractors to begin work on reopening some of the streets around the square. The work is expected to be completed in three weeks.

    It is also involved in negotiations to try to find a way of completing the main redevelopment work in the square. It says it is now likely that that may not be completed until early next year.

    #752146
    PTB
    Participant

    6.5 million

    It was up to 9 before this whole latest incident began.10 or 11 looks like the finishing cost and I think that the City Council will be sued for compensation due to some of the shops closing down due to loss of buisness so that could be a further cost.

    P.S When did it start and when was it due to finish?

    #752147
    Boyler
    Participant

    Let’s just say that the Empire State Building in New York was built faster than this project.