Connolly/LUAS
- This topic has 2 replies, 2 voices, and was last updated 22 years, 11 months ago by
GrahamH.
- AuthorPosts
- February 10, 2003 at 6:55 pm #706004
GrahamH
ParticipantDidn’t someone say the huge stone wall at the back of the ramp of Connolly is staying put, due to concerns of residents in the apartments? Well it ain’t!
Had a good gawk today onto the site, and stood watching as the granite blocks began to tumble down, from the efforts of diggers etc. There’s a massive pile of beautiful granite sitting on site, and thats only a few strands from the top part of the wall!
The canopy entrance to the station at the top of the ramp is also being dismantled.
- February 11, 2003 at 9:48 am #724461
JJ
ParticipantGraham,
some of the stone work is being retained for re-use to clad the new stairs to the upper levels on Amiens Street side and a new retaining wall on Harbourmaster Place.BTW the stone is mostly Limestone of which there are three distinct types and finishes.The only granite is in a string course and a couple of cills.
The centre of the ramp is constructed from brick arching and over the next few weeks this should become visible.
JJ
- February 11, 2003 at 11:04 pm #724462
GrahamH
ParticipantI pass every day, can’t wait! I’ll get some pics.