Cost of repairing wobbly bridge could rise to £10m
Within the next two weeks engineer Ove Arup will unveil its proposals to stop the wobbling Millennium Bridge from swaying at an estimated cost of £2 million. There are serious concerns, however, that Lord Foster’s Thames footbridge will need a further £10 million of remedial work before it can be opened to the public.
Ove Arup is expected to favour a system of dampers to bring stability to the £18 million "blade of light", a method which some experts believe will be ineffective. "Maybe dampers will work," said the Tokyo-based bridge specialist, Professor Yozo Fujino, "but I’m not very confident. The problem is that the bridge is very light and human forces are very large."
Fujino identified the problem of "synchronised footfall" in a paper written in 1993. This report has subsequently been consulted by engineers around the world including Techniker, the firm behind London’s Royal Victoria Dock footbridge that opened in 1998. "If you do advanced and sophisticated things, then you should make sure you read the literature first," said Techniker’s director Mathew Wells.
Ove Arup failed to consult Fujino’s paper, considering it to be obscure, but it did undertake "dynamic analyses" and wind tunnel tests as well as consulting an independent firm of engineers before proceeding with the design.
Another bridge expert, Dr Arvind Kumar, advises the Corporation of London and was one of over 200 entrants in the Millennium Bridge design competition. Kumar believes that more drastic measures are needed to make the bridge safe. "You can’t totally rectify the bridge except by raising the height of the cables which would cost up to £10 million," he said.
Whatever solution Ove Arup propose, it is clear that the cost will run into of millions of pounds. What is not clear as of yet is where this additional funding will come from. The Millennium Commission, private financiers and the project’s insurers can all expect a visit in the near future.
Within the next two weeks engineer Ove Arup will unveil its proposals to stop the wobbling Millennium Bridge from swaying at an estimated cost of £2 million. There are serious concerns, however, that Lord Foster’s Thames footbridge will need a further £10 million of remedial work before it can be opened to the public.
Ove Arup is expected to favour a system of dampers to bring stability to the £18 million "blade of light", a method which some experts believe will be ineffective. "Maybe dampers will work," said the Tokyo-based bridge specialist, Professor Yozo Fujino, "but I’m not very confident. The problem is that the bridge is very light and human forces are very large."
Fujino identified the problem of "synchronised footfall" in a paper written in 1993. This report has subsequently been consulted by engineers around the world including Techniker, the firm behind London’s Royal Victoria Dock footbridge that opened in 1998. "If you do advanced and sophisticated things, then you should make sure you read the literature first," said Techniker’s director Mathew Wells.
Ove Arup failed to consult Fujino’s paper, considering it to be obscure, but it did undertake "dynamic analyses" and wind tunnel tests as well as consulting an independent firm of engineers before proceeding with the design.
Another bridge expert, Dr Arvind Kumar, advises the Corporation of London and was one of over 200 entrants in the Millennium Bridge design competition. Kumar believes that more drastic measures are needed to make the bridge safe. "You can’t totally rectify the bridge except by raising the height of the cables which would cost up to £10 million," he said.
Whatever solution Ove Arup propose, it is clear that the cost will run into of millions of pounds. What is not clear as of yet is where this additional funding will come from. The Millennium Commission, private financiers and the project’s insurers can all expect a visit in the near future.